CTH X (Hart Rd - Clinton)
Anticipated Closure for Construction: April 1st - May 30th
- Signing 6/2/25 โ 6/5/25.
- Open by end of day on 6/6/25
CTH T (Hafeman Rd - 23rd St.)
Anticipated Closure for Construction: April 14th -June 30th
- Paving and shouldering will be completed by 6/6/25
- Painting and signing 6/9/25 โ 6/13/25
- Open by end of day on 6/13/25
CTH B (STH 213 - Coon Island Rd)
Anticipated Closure for Construction: April 21st - July 18th
- Culvert work continues 6/2/25 - 6/5/25
- Pulverizing begins 6/9/25 - 6/13/25
- Culvert work continues 6/16/25 - 6/26/25
- Paving begins 6/30/25 - 7/10/25
- Striping and signing 7/14/25 - 7/18/25
- Open by end of day 7/18/25
CTH H (USH 14 to STH 11)
Design 2025, Real Estate and Utilities 2025-2026, Construction 2027-2028
CTH H PIM Letter
CTH H PIM Handout